Street Closures
The following streets are scheduled to be closed.



CCLSDI – Linford School Drainage Improvements

City Project Manager:
William Winkler, 307-721-5273,

Contractor:
Hamaker Excavation Inc.

Project Location:
Waterline and Storm Sewer Map
Street Improvements Map

Project Description:
The City has contracted with Hamaker Excavation Inc. to complete waterline, storm sewer, and roadway improvements in the area around the Linford Elementary School.  This work will include the installation of an underground detention system within the school parking lot.  Access will be limited to local residents during the construction.

Scheduled Completion Date:
All work within Johnson Street and Wyoming Avenue is scheduled to be completed by August 19th, 2016.  The work within Grant Street, Jefferson Street, and Colorado Avenue is scheduled to be completed by November 4th, 2016.

Additional Information:


Date Updated: 9/26/2016

 ==================================================

WWMP - Wastewater Master Plan Project
City Project Manager:
Earl Smith,

Project Description:
The City of Laramie has entered into a professional services agreement with Burns & McDonnell for the Wastewater Master Plan. 


Date Updated: 9/26/2016

===================================================

WTLGA2 - Water Line Replacement - Grand Ave

City Project Manager:
William Winkler, 307-721-5273,

Project Location:
Grand Avenue between 15th Street and 13th Street

Project Description:
A request for qualifications has been made by the City of Laramie to design a water line replacement between 15th street and 13th street on Grand Avenue.  All RFQ's need to be submitted by 3:00 pm on October 3rd.


Date Updated: 9/26/2016 

 ==================================================

WWSLSL – South Laramie Sanitary Sewer Project

City Project Manager:
William Winkler, 307-721-5273,

Contractor:
Simon Contractors

Project Location:
Work is wrapping up as the contractor is completing the project.

Project Description:
Simon Contractors is contracted to complete upgrades to the City's sanitary sewer system.  Along with the sewer installation the roadways will be repaired.

Simon Contractors is reaching the south end of 2nd Street with the installation of sanitary sewer pipe.  As this work continues access will be provided to the local businesses but caution should be used as the work zone is very congested. 

Scheduled Completion Date:
All work for this project is scheduled to be completed by July 24th, 2016.

Date Updated: 9/26/2016

===================================================


Ivinson Street Reconstruction – Public Meeting Exhibits
City Project Manager:
Eric Jaap,

Consultant:
Trihydro Corporation

Project Location:
Project Location

Project Description:
The City contracted with Trihydro to develop a conceptual design for the future reconstruction of Ivinson Street, 10th Street, 11th Street, 12th Street, 13th Street, 14th Street, and 15th Street adjacent to the south side of the University of Wyoming campus.  City staff is interested in hearing public comments regarding the conceptual design.

Scheduled Completion Date:
The conceptual design has been completed.