City Projects - Updated: 4/21/17

CCCSTR (Cirrus Sky Technology Park Trail Project)
City Project Manager: Todd Feezer  
Design Consultant:  Western Research and Development
Contractor:  Simon Contractors
Project Location: 22nd & Cumulus Drive
Project Description:   Construction of a hike/bike trail along the southern edge of Cirrus Sky Technology Park.
Scheduled Completion Date: Fall 2017
Status: In design

CCHSMT (Harney St. Viaduct) – WYDOT, 745-2100
City Project Manager: William Winkler
Contractor:  S&S Builders
Project Location: 3rd and Harney
Project Description:   Construction of a new bridge (bypass) connection to Snowy Range Road. 
Scheduled Completion Date:  Fall 2018
Status: Demo started. Currently Harney Street West of 3rd Street is closed, as well as Railroad Street East of Cedar Street and a portion of Snowy Range Road between Cedar St and Garfield St.

GFSR15 (15th Street Reconstruction)
City Project Manager: William Winkler
Design Consultant:   WWC Engineering
Contractor:  TBD
Project Location: 15th Street between Bill Nye Ave. and the I-80 bridge.
Project Description:   Upgrading Water & Sewer lines. 
Scheduled Completion Date:  Fall 2017
Status: In design

GFSR18 (18th Street Reconstruction)
City Project Manager: William Winkler
Design Consultant:   WWC Engineering
Contractor:  TBD
Project Location: 18th Street between Rainbow Ave. and Sheridan St.
Project Description:   Upgrading Water & Sewer lines. 
Scheduled Completion Date: Fall 2017
Status: In design

GFSRML (SPT Schedule 4 Phase 4 - Mill Street)
City Project Manager: William Winkler
Design Consultant:   Coffey
Contractor:  TBD
Project Location:  Mill Street between 10th St. and 13th St.
Project Description: Upgrading Water & Sewer lines. 
Scheduled Completion Date:  Fall 2017
Status: In design

WTLGA2 Grand Avenue Waterline replacement
City Project Manager: William Winkler
Design Consultant:   Trihydro
Contractor:  TBD
Project Location: Grand Avenue, 13th to 15th Street
Project Description:    Upgrading Water & Sewer lines. 
Scheduled Completion Date:  Fall 2017
Status: In design

WTLMTS (Mitchell Street Water Line Replacement)
City Project Manager: William Winkler
Design Consultant:   JUB
Contractor:  TBD
Project Location:  Mitchell Street between 15th Street and 18th Street.
Project Description:    Upgrading Water & Sewer lines. 
Scheduled Completion Date:  Fall 2017
Status: In design

WTNSTK (North Side Tank)
City Project Manager:  Earl Smith
Design Consultant:  DOWL
Contractor:  TBD
Project Description: New water storage tank for north Laramie
Project Location: Fall 2018
Status: In design

WTP111 (11th Street Waterline Replacement)
City Project Manager:
Consultant:   DOWL
Contractor:  TBD
Project Location:  11th Street between Russell St. and Steele St.
Project Description:   Upgrading Water & Sewer lines. 
Scheduled Completion Date:  Fall 2017
Status: In design

WWBA07 (Banner Road)
City Project Manager:
Consultant:   Trihydro
Contractor: Simon Contractors
Project Location: Banner road north of Curtis
Project Description:   Upgrading Water & Sewer lines. 
Scheduled Completion Date:  Fall 2018
Status: In design

WWCLH6 (C-Line Replacement Hancock to Canby/Canby to 6th)
City Project Manager:
Consultant:   Trihydro
Contractor:  TBD
Project Location:  2nd Street from Hancock St. and Canby St. and Canby Street from 2nd St. to 6th St.
Project Description:  Upgrading Water & Sewer lines. 
Scheduled Completion Date:  Fall 2017
Status: In design